A milestone moment this week for the Pelican Waters project with bulk earthworks for the whole site now complete. Earthworks operations for the canals commenced over 40 years ago and over the years over five million cubic metres of excavation has taken place.
Over the past week lots associated with the final stages of the project have been drill seeded and hydroseeded. The remaining lake batters have also been turfed.
With well over 3,000 lots sold in Pelican Waters it’s remarkable to consider only 69 more to go!
A project of this scale and longevity can’t happen without a lot of hard work. Some key team members of the team photographed below from left to right Hamish Pressland CEO, Dane Alexander Landscape Manager, Nigel Holley Senior Supervisor SEE Civil, Michael Fields Construction Manager SEE Civil, Phil Tyrer Project Manager, Chris Temmerman Civil Engineer Covey Associates. A big thanks to the consultants and contractors, some of whom have worked on the job for over 40 years.